A 'Cost Down' Genba Kanri Strategy |
Background |
This client is a well-respected UK manufacturer of fluid control mechanisms. Although celebrating its centenary, it is seeing many of its domestic competitors falter in the face of ever-cheaper imports. It introduced an operational structure more appropriate to the 21st Century; invested in educating its First Line Managers - but it needs results! |
||||||
It needed to: |
~ |
improve the skills of its people |
~ |
apply GK |
~ |
put money in the till |
An exploratory Workshop took place: there was some scepticism: 'Genba Kanri?' yet another 'snake oil' remedy?! It was decided to focus on a machining/ assembly facility which was already one of the best on site in terms of output per person, and with an enthusiastic Team Leader. |
Initial Workshop Objectives: |
|
~ |
Test the Approach |
|
~ |
Validate the Benefits |
|
~ |
Move from Education to Training |
|
~ |
Enrol Support Functions |
............................................. | ||
A glance at the area confirmed the work paradigm: "Pile 'em high and go like the clappers!" | ||
On the machine changeover, the biggest surprise was the lack of a standard method - it had been assumed that there was one! The operator spent a lot of time walking from round the machine - see spaghetti diagram... |
|||
Over the three days of the Workshop, two sub-teams looked at Assembly and Changeovers. Results (not 'proposals') were effectively achieved in two days - but they were re-confirmed a month after the event to ensure they were sustained! | Challenge | Target | Actual |
Reduce Assembly Time | 10% | 13% | |
Reduce Floor-to-Floor Time | 20% | 90% | |
Reduce Changeover Time | 20% | 36% | |
The total costs of the Workshop, including hardware, overtime payments and consultancy fees were £7,102; the total savings £10,321 - so that put money in the till. | |||
More importantly, the seeds had been sown for Genba Kanri - better management and improvement of the area. Nine months later, further improvements had increased productivity by 160%. |
................................................................................................... |
|
Fifteen more Workshops were conducted around
the plant on a variety of themes. Over the following nine months, savings
resulting directly from Workshops and follow-on activities - when
people started doing it for themselves - exceeded half a million
pounds!
Common physical changes were the introduction of one piece flow; cellular manufacturing and the linking/balancing of processes. |
.......................................................................................................................................... |
This initial phase of Genba Kanri brought better standards for 'what' and 'how' - defining what exactly is expected, and the best known method of achieving it; better materials management; better target control, and increased confidence and competence for people to make autonomous improvements. |
RETURN TO MAIN PAGE |
The web site dedicated to improving manufacturing competitiveness |
genba-kanri.com |